IAS 11: Construction Contracts

Summary of IAS 11

Objective of IAS 11

The objective of IAS 11 is to prescribe the accounting treatment of revenue and costs associated with construction contracts.

What is a construction contract?

A construction contract is a contract specifically negotiated for the construction of an asset or a group of interrelated assets. [IAS 11.3]
Under IAS 11, if a contract covers two or more assets, the construction of each asset should be accounted for separately if (a) separate proposals were submitted for each asset, (b) portions of the contract relating to each asset were negotiated separately, and (c) costs and revenues of each asset can be measured. Otherwise, the contract should be accounted for in its entirety. [IAS 11.8]
Two or more contracts should be accounted for as a single contract if they were negotiated together and the work is interrelated. [IAS 11.9]
If a contract gives the customer an option to order one or more additional assets, construction of each additional asset should be accounted for as a separate contract if either (a) the additional asset differs significantly from the original asset(s) or (b) the price of the additional asset is separately negotiated. [IAS 11.10]

What is included in contract revenue and costs?

Contract revenue should include the amount agreed in the initial contract, plus revenue from alternations in the original contract work, plus claims and incentive payments that (a) are expected to be collected and (b) that can be measured reliably. [IAS 11.11]
Contract costs should include costs that relate directly to the specific contract, plus costs that are attributable to the contractor's general contracting activity to the extent that they can be reasonably allocated to the contract, plus such other costs that can be specifically charged to the customer under the terms of the contract. [IAS 11.16]

Accounting

If the outcome of a construction contract can be estimated reliably, revenue and costs should be recognised in proportion to the stage of completion of contract activity. This is known as the percentage of completion method of accounting. [IAS 11.22]
To be able to estimate the outcome of a contract reliably, the entity must be able to make a reliable estimate of total contract revenue, the stage of completion, and the costs to complete the contract. [IAS 11.23-24]
If the outcome cannot be estimated reliably, no profit should be recognised. Instead, contract revenue should be recognised only to the extent that contract costs incurred are expected to be recoverable and contract costs should be expensed as incurred. [IAS 11.32]
The stage of completion of a contract can be determined in a variety of ways - including the proportion that contract costs incurred for work performed to date bear to the estimated total contract costs, surveys of work performed, or completion of a physical proportion of the contract work. [IAS 11.30]
An expected loss on a construction contract should be recognised as an expense as soon as such loss is probable. [IAS 11.22 and 11.36]

Disclosure

  • amount of contract revenue recognised; [IAS 11.39(a)]
  • method used to determine revenue; [IAS 11.39(b)]
  • method used to determine stage of completion; [IAS 11.39(c)] and
  • for contracts in progress at balance sheet date: [IAS 11.40]
    • aggregate costs incurred and recognised profit
    • amount of advances received
    • amount of retentions

Presentation

The gross amount due from customers for contract work should be shown as an asset. [IAS 11.42]
The gross amount due to customers for contract work should be shown as a liability. [IAS 11.42]

Comments

Popular posts from this blog

DOWNLOADABLE QUICKBOOKS PRO 2021 and older versions (Complete Package)

Enjoy full and complete access to your QuickBooks softwares by entering the License Numbers and Product Numbers below.  If you find this article very helpful, please donate  US $1  only through paypal.  Just click the "PAYPAL" icon below and this is a big help to support us in continuing this blogsite. (please donate through PayPal and enjoy cost-free and hassle-free quick books software by Intuit) QUICKBOOKS PRO ENTERPRISE (UK) 2021 License Number: 7482 8847 2621 492 Product Number:  919 801 QUICKBOOKS PRO ENTERPRISE 2020 License Number: 9068 3838 2777 984 Product Number: 875 560 QUICKBOOKS PRO NON-ENTERPRISE 2021 License Number: 1063 0575 1585 222 Product Number:  833 891 or 016 376 QUICKBOOKS PREMIER ACCOUNTANT US 2021 License Number:  2060 3140 2137 757 Product Number: 919 801 (note: alternative license to Pro Enterprise 2021 - no need for validation code) QUICKBOOKS PRO ENTERPRISE 2021 UK EDITION License Number:  5108 5360 0832 409 Product

OPERATIONS AUDIT: WRITTEN ASSIGNMENT WEEK 5

Submit a 2-3 pages paper assignment, (excluding the title page and reference page) double-spaced in  Times New Roman  font which is no greater than  12-points in size . Paper and all citations should be in APA format. Send it to  maggrabillo@rtu.edu.ph  once completely accomplished.    1. List the 7 Es according to importance or with the greatest impact on the organization. Explain how they impact the business. 2. Link the concept of excellence to the work of internal auditors and how can it be incorporated in audit programs. 3. How can failure in ethics affect organizational success? Choose one company that failed as to its ethics. 4. Describe ways to monetize the concept of ecology. How can you encourage others to observe environmental stewardship? After sending through email,  kindly post in rich text format your case analysis by commenting  on this post.  Deadline for accomplishment:  November 28, 2021 11:59PM

OPERATIONS AUDIT: DISCUSSION ASSIGNMENT WEEK 8

PROJECT MANAGEMENT & CHANGE MANAGEMENT Project management and change management are often confused. Although they both involve managing people and processes (and often work together to meet organizational goals), they are different disciplines (Lucid, n.d.). Understanding what those differences are and how both practices can (and should) work together to manage projects and their resulting changes is crucial for the success of your organization. The term “project management” can at once feel both obvious and vague. While most people intuitively understand what project management is, it’s useful to refer to the official definition. Project management is described as the application of knowledge, skills, tools, and techniques to meet project requirements. In other words, project management is about the process required to bring a team or product from point A to point B. To do this, project managers and their teams manage processes within five main project stages: Initiating Planning